Pending

No upcoming vote or hearing detected in the documents we have read.

History

Hearing notice Moratorium Battery storage (BESS)
Town Board · · Westchester County
“earing On A Local Law Extending The Moratorium On Battery Energy Storage Systems Over 81kWh for September 8, 2026 at 6:05 p.m. Documents: BEDFORD - LOCAL LAW - BESS MORATORIUM EXTENSION (REVISED 08- 04-2026)…”
Source document, p. 4 (opens in a new tab) Packet for Aug 11, 2026 +1 related mention
Adopted Moratorium Battery storage (BESS)
Town Board · · Westchester County
“AL OF APPLICATIONS AND ISSUANCE OF PERMITS FOR LARGE-SCALE "BATTERY ENERGY STORAGE SYSTEMS" IN THE TOWN OF BEDFORD LOCAL LAW NO. OF 2026 A Local Law Adopting A Moratorium on Large Scale “Battery Energy Storage Systems”…”
Extended Moratorium Battery storage (BESS)
Town Board · · Westchester County
“AL OF APPLICATIONS AND ISSUANCE OF PERMITS FOR LARGE-SCALE "BATTERY ENERGY STORAGE SYSTEMS" IN THE TOWN OF BEDFORD LOCAL LAW NO. OF 2026 A Local Law Adopting A Moratorium on Large Scale “Battery Energy Storage Systems”…”
Public hearing Moratorium Battery storage (BESS)
Town Board · · Westchester County
“ring On A Local Law Extending The Moratorium On Large Scale Battery Energy Storage Systems In The Town Of Bedford For 6 Months Documents: BEDFORD - LOCAL LAW - BESS MORATORIUM EXTENSION (REVISED 08- 04-2026)…”
Source document, p. 1 (opens in a new tab) Packet +1 related mention
Adopted Moratorium Battery storage (BESS)
Town Board · · Westchester County
“AL OF APPLICATIONS AND ISSUANCE OF PERMITS FOR LARGE-SCALE "BATTERY ENERGY STORAGE SYSTEMS" IN THE TOWN OF BEDFORD LOCAL LAW NO. OF 2026 A Local Law Adopting A Moratorium on Large Scale “Battery Energy Storage Systems”…”
Extended Moratorium Battery storage (BESS)
Town Board · · Westchester County
“AL OF APPLICATIONS AND ISSUANCE OF PERMITS FOR LARGE-SCALE "BATTERY ENERGY STORAGE SYSTEMS" IN THE TOWN OF BEDFORD LOCAL LAW NO. OF 2026 A Local Law Adopting A Moratorium on Large Scale “Battery Energy Storage Systems”…”

Enacted moratoria on record

  • 2024-08-13 · Battery storage (BESS)
    Town of Bedford local law prohibiting review and approval of applications for battery energy storage systems (Local Law No. 1-2025 extending the original 2024-08-13 moratorium)