Pere Marquette Charter Township, MI
Adopted: data center siting ordinance, Township Board; meeting Sep 8, 2026. The notice text is not reproduced here; open the original notice to read it.
Status of all 21 local governments in Mason County (the county and its townships, cities and villages) on moratoria and siting rules for data centers, battery storage, solar and wind.
Data last changed (02:41 UTC) · page regenerated daily, last on
Townships/towns with cities and villages drawn on top. Boundaries: Census TIGER/Line 2025.
No upcoming hearing or vote detected in the 16 governments we monitor here.
| Government | Moratorium status | Latest or next item | Sources monitored |
|---|---|---|---|
| Mason County | None known | — | 2 |
| Pere Marquette Charter Township | In force Data centers: Active (Moratorium Nation, enacted Aug 11, 2026) |
Adopted: data center siting ordinance · | 6 |
| Sherman Township | Adopted Data centers: Adopted, Apr 21, 2026 |
Adopted: data center moratorium · | 2 |
| Amber Township | None known | — | 1 |
| Branch Township | None known | — | 2 |
| City of Ludington | None known | — | 2 |
| City of Scottville | None known | — | 1 |
| Custer Township | None known | — | 1 |
| Eden Township | None known | — | 2 |
| Free Soil Township | None known | — | 2 |
| Grant Township | None known | — | 2 |
| Hamlin Township | None known | — | 5 |
| Logan Township | None known Not monitored yet
|
— | 0 |
| Meade Township | None known Not monitored yet
|
— | 0 |
| Riverton Township | None known | — | 1 |
| Sheridan Township | None known | — | 1 |
| Summit Township | None known | — | 1 |
| Victory Township | None known | — | 1 |
| Village of Custer | None known Not monitored yet
|
— | 0 |
| Village of Fountain | None known Not monitored yet
|
— | 0 |
| Village of Free Soil | None known Not monitored yet
|
— | 0 |
“None known” means no record in Moratorium Nation and nothing detected in the documents we read; for governments we do not monitor yet it says nothing either way.
Adopted: data center siting ordinance, Township Board; meeting Sep 8, 2026. The notice text is not reproduced here; open the original notice to read it.
Adopted: data center moratorium, Township Board; meeting Aug 25, 2026. The notice text is not reproduced here; open the original notice to read it.
Adopted: data center moratorium, Township Board; meeting Aug 11, 2026. The notice text is not reproduced here; open the original notice to read it.
Hearing notice: data center moratorium, Planning Commission; meeting Aug 4, 2026. The notice text is not reproduced here; open the original notice to read it.
Adopted: data center moratorium, Township Board; meeting Jul 14, 2026. The notice text is not reproduced here; open the original notice to read it.
| Date | Government | Uses | Status | Details and source |
|---|---|---|---|---|
| Pere Marquette Charter Township | Data centers | In force Active |
Ordinance No. 162 (temporary data center moratorium, adopted 2026-08-11) and Ordinance No. 163 (zoning ordinance amendment adding Article 33.07,... (Moratorium Nation) Earlier item in our records: On the agenda (before the vote), Jul 14, 2026 |
|
| Sherman Township | Data centers | Adopted Adopted, Apr 21, 2026 |
Data center moratorium adopted — Township Board, Apr 21, 2026. Source document (opens in a new tab) (Siting Radar) |
Moratorium records marked “Moratorium Nation” come from the Moratorium Nation inventory by Michael J. Bommarito, licensed CC BY 4.0; status follows that inventory, and we mark a record ended once its recorded end date has passed. Records marked “Siting Radar” are our own detections in public meeting documents: the status is the latest step we saw, with a link to the source. Not legal advice.
As of Sep 30, 2026, our records show data center moratorium activity in Pere Marquette Charter Township (in force) and Sherman Township (adopted) in Mason County. See the table on this page for dates and sources.
None known as of Sep 30, 2026. We monitor 16 of 21 governments in Mason County, so a moratorium could exist without appearing here.
None known as of Sep 30, 2026. We monitor 16 of 21 governments in Mason County, so a moratorium could exist without appearing here.
None known as of Sep 30, 2026. We monitor 16 of 21 governments in Mason County, so a moratorium could exist without appearing here.
It is regenerated daily from the documents we monitor and the Moratorium Nation inventory. Page generated Sep 30, 2026. Not legal advice.