“This landscape plan was inclusive of the substation and is identical to the landscape plan submitted for the data center site plan.”
Van Buren Charter Township, Michigan
Moratoria, zoning amendments and siting ordinances for data centers, battery storage, solar and wind in Van Buren Charter Township (Wayne County).
Pending
No upcoming vote or hearing detected in the documents we have read.
History
“4,930 SF Yes 3,873 SF Charter Township of Van Buren – VBT-25-04 (Project Cannoli – Data Center) SPR #4 – Final Site Plan 6 August 19, 2026”
“NEW BUSINESS: ITEM # 1: Case 25-041 - Project Cannoli Data Center – Final Site Plan Approval”
“Fellow commissioner commented to maybe put a moratorium on that one. • Commissioner commented he doesn’t know which one the Commission would want to do first the soil mining or industrial uses, because that includes the…”
“To consider denial of a special land use request by Stag Horn, LLC to install a 200 MW Battery Energy Storage System, with supporting infrastructure on parcel 83-123-99-0001-003.”
Hearing notice: battery storage project application, Planning Commission; meeting May 13, 2026. The notice text is not reproduced here; open the original notice to read it.
Adopted: data center moratorium, Planning Commission; meeting Feb 11, 2026. The notice text is not reproduced here; open the original notice to read it.
On the agenda (before the vote): data center moratorium, Board of Trustees; meeting Jan 20, 2026. The notice text is not reproduced here; open the original notice to read it.
Adopted: battery storage zoning amendment, Board of Trustees; meeting Jul 15, 2025. The notice text is not reproduced here; open the original notice to read it.
Adopted: battery storage zoning amendment, Board of Trustees; meeting Jul 1, 2025. The notice text is not reproduced here; open the original notice to read it.
On the agenda (before the vote): battery storage zoning amendment, Board of Trustees; meeting Jul 1, 2025. The notice text is not reproduced here; open the original notice to read it.