Home › Georgia › Monroe County

Monroe County, Georgia

Moratoria, zoning amendments and siting ordinances for data centers, battery storage, solar and wind in Monroe County.

Pending

No upcoming vote or hearing detected in the documents we have read.

Enacted moratoria on record

  • 2025-12-02 · Data centers
    Resolution on Data Center Moratorium prepared by Brandon Bowen of Jenkins, Bowen & Walker, P.C., approved 4-1 on 2025-12-16, superseded by a permanent ordinance amending the Monroe County Unified Development Ordinance (restricting data centers to Special Use in M-1 zoning; adding setback, buffer, generator, lighting, sound, and utility standards), posted by the county as agenda item '04-07-26 C. Data Center Ordinance Amendment' and, per a county Facebook post, unanimously approved by the Board of Commissioners on April 7, 2026.

Source: Moratorium Nation (Michael J. Bommarito), CC BY 4.0. Matched to this jurisdiction by name and location; check the original record.