Coweta County, Georgia

Moratoria, zoning amendments and siting ordinances for data centers, battery storage, solar and wind in Coweta County.

Pending

No upcoming vote or hearing detected in the documents we have read.

History

On the agenda (before the vote) Siting ordinance Data centers
Board of Commissioners ·
“…Discussion Regarding the Coweta County Data Center Ordinance Issue: Discussion Regarding the Coweta County Data Center Ordinance Discussion: At the Work Session on July 14, 2026, the Board directed staff to prepare an…”
On the agenda (before the vote) Siting ordinance Data centers
Board of Commissioners ·
“…Discussion Regarding the Coweta County Data Center Ordinance Issue: Discussion Regarding the Coweta County Data Center Ordinance Discussion: At the Work Session on July 14, 2026, the Board directed staff to prepare an…”
Source document, p. 2 (opens in a new tab) Packet +2 related mentions
Adopted Siting ordinance Data centers
Board of Commissioners ·
“…stating that the project meets all requirements of the County's Data Center Ordinance, including closed-loop cooling, Tier four (4) generators, restricted generator testing hours, watershed protection, and buffer…”
On the agenda (before the vote) Project application Data centers
Board of Commissioners ·
“Blackwell explained that the submitted site plan depicts a five-building data center campus totaling approximately 1,828,368 square feet of gross floor area.”
Public hearing Moratorium Data centers
Board of Commissioners ·
“24 (Petition # REZ 24-20) application submitted requesting to rezone 209.84± acres (Parcel # 096-5142-001) from RC (Rural Conservation) to M (Industrial) for a proposed data center campus.”

Enacted moratoria on record

  • 2026-06-16 · Data centers
    (second instrument, June 2026) Coweta County Board of Commissioners resolution imposing a 180-day moratorium on acceptance of permits, land use amendments, rezoning/conditional use and variance applications and public hearings related to data centers (2026 review of the December 2025 data center ordinance)
  • 2025-05-06 · Data centers
    (first instrument, May 2025) Board of Commissioners moratorium resolution; replaced by permanent data center ordinance posted at https://www.coweta.ga.us/home/showpublisheddocument/32598/639016609046670000 [VERIFY: Coweta civic-clerk portal blocks direct PDF download (HTTP 403); ordinance number not yet retrieved as of 2026-04-29]